Encom’s biggest asset is its people whose talent helps us to drive our business forward with the same passion for engineering. Encom takes initiative, continuously improves, grows and cover a wide range of services. We create significant value for our customers through uncompromising professionalism in all that we do.

 

Skills:

  • Trust
  • Professionalism
  • Growth
  • Innovation
  • Transparency
  • Achievement and excellence
Follow Us On Social
 

Project 374 – New Pump Station Unl95/ADO Engineering Study

About This Project

Client: EKO – HELPE

Status: Ongoing

Completion Date: 15/07/2020

 

Piping Scope:

  • 3d Model Design
  • Piping Isometrics, Layouts & MTO
  • Stress Analysis, Piping Supports MTO
  • Isometric Sketch List

Process Works Scope:

  • Preparation Of Hydraulic Calculations For Suction Lines
  • Preparation Of P&Ids
  • Mechanical Line List

 

Instrument Works Scope:

  • Instrument List
  • Dcs/Esd Database
  • Cable List
  • I/O Count
  • Mechanical Hook-Up Drawings
  • Mechanical Hook-Up MTO
  • Junction Boxes Wiring Drawings
  • Electr / Instr Interface Drawings
  • Instrument Cable Routing Drawings
  • Instrument Cable Routing Sections
  • Instrument & Junction Boxes Layout
  • Cable Trays & Accessories MTO
  • Junction Boxes And Materials MTO
  • Logic Diagrams
  • Graphic Displays Sketches
  • Loop Drawings
  • D/S For Motorised Valves
  • D/S For Safety Valves
  • D/S For Pressure Transmitters
  • D/S For Pressure Gauges
  • SCADA MTO
  • SCADA Wiring

Electrical Works scope:

  • Electrical Basis of Design, Technical Description
  • Material Take offs (Power and Grounding Materials)
  • Existing Substation One Line Diagram (update/modification of related MCC)
  • Typical Schematic Diagram (LV Motor + Local Control Station)
  • Wiring Interconnecting Diagram (LV Motor & LCS with Marshalling Cabinet)
  • Cable sizing Calculation Report
  • Electrical Cable Routing Layout(S)
  • Electrical Cable Routing Cross Sections dwgs
  • Electrical Cable Schedule
  • Electrical Consumer List (“from – to” List)
  • Grounding System Installation layout
  • Typical Installation Details applied for Cable routing
  • Typical Installation Details applied for Grounding Installation

Civil works scope:

  • Calculation Report for Concrete Foundation of No 4 Pumps
  • Drawings for Concrete Foundation of No 4 Pumps
  • MTO for Concrete Foundation of No 4 Pumps
  • Calculation Report for Steel Structure with Platform
  • Drawings for Steel Structure with Platform
  • MTO for Steel Structure with Platform
  • Calculation Report for Foundation of Steel Structure with Platform
  • Drawings for Foundation of Steel Structure with Platform
  • Calculation Report for Steel Structure with Platform
  • Drawings for Steel Structure with Platform
  • MTO for Steel Structure with Platform
  • Calculation Report for Foundation of Steel Structure with Platform
  • Drawings for Foundation of Steel Structure with Platform
  • MTO for Foundation of Steel Structure with Platform
  • Calculation Report / Adequacy Check for New Added Deck on Existing Pipe Rack
  • Drawings for New Added Deck on Existing Pipe Rack
  • MTO for New Added Deck on Existing Pipe Rack
  • Calculation Report for New Added Deck on Existing Pipe Rack
  • Drawings for New Added Deck on Existing Pipe Rack
  • MTO for New Added Deck on Existing Pipe Rack

Price List for Civil Works